# The Chester Guided Busway Order 2002, Paragraph 1


(1) In this Part of this Schedule—
“construction” includes placing, alteration and reconstruction; and “construct” and “constructed” shall be construed accordingly;
“plans” includes sections, specifications and method statements;
“sewer” means a public sewer within the meaning of the Water Industry Act 1991, and includes a disposal main within the meaning of that Act and any manholes, ventilating shafts, pumps or accessories forming part of any such sewer; but the provisions of paragraphs 4 to 9 do not apply to any sewer in respect of which relations between the Council and the undertaker are regulated by the provisions of Part III of the 1991 Act;
“specified work” means so much of any of the authorised works as is situated over, or within 15 metres of, or (wherever situated) imposes any load directly upon, any sewer; and
“the undertaker” means the sewerage undertaker for the area within which the authorised works are situated or whose sewers are affected by those works.
(2) The provisions of Schedule 5 to this Order shall not apply in relation to apparatus to which this Part of this Schedule applies.

---
Source: https://www.legislation.gov.uk/uksi/2002/412/schedule/6/part/IV/crossheading/interpretation/paragraph/1 (the official version)
Page: https://openlegislation.uk/chester-guided-busway-order-2002/schedule-6/part-IV/crossheading-interpretation/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.