# The Chiltern Railways (Bicester to Oxford Improvements) Order 2012, Paragraph 11

Extent: E+W+S

The Company must bear the reasonable costs of the carrying out, by a qualified surveyor or engineer (“the surveyor”) to be appointed by the Trust and Company, of surveys of so much of the canal as will or may be affected by the specified works—
(a) before commencement of the initial construction of any part of the specified works; and
(b) following completion of the specified works,
and if the Trust and the Company do not agree on the appointment of the surveyor under this paragraph an arbitrator is to be appointed on the application of either party (after giving notice in writing to the other) by the President of the Institution of Civil Engineers.

---
Source: https://www.legislation.gov.uk/uksi/2012/2679/schedule/17/paragraph/11 (the official version)
Page: https://openlegislation.uk/chiltern-railways-bicester-to-oxford-improvements-order-2012/schedule-17/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.