{
  "url": "https://openlegislation.uk/cleve-hill-solar-park-order-2020/schedule-1/paragraph-12",
  "json_url": "https://openlegislation.uk/cleve-hill-solar-park-order-2020/schedule-1/paragraph-12.json",
  "legislation": "uksi/2020/547",
  "legislation_title": "The Cleve Hill Solar Park Order 2020",
  "legislation_url": "https://openlegislation.uk/cleve-hill-solar-park-order-2020",
  "path": "schedule/1/paragraph/12",
  "kind": "paragraph",
  "number": "12",
  "heading": "Construction traffic management plan",
  "text": "(1) No phase of the authorised development may commence until written details of a construction traffic management plan (which must accord with the outline construction traffic management plan) for that phase has been submitted to and approved by the relevant planning authority in consultation with the relevant highway authority.\n(2) The construction traffic management plan must be implemented as approved.",
  "extent": "E+W+S+N.I.",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 Pt. 2 para. 12 in force at 19.6.2020, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2020/547/schedule/1/paragraph/12",
    "retrieved_at": "2026-10-28T22:29:58.694290+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}