# The Cleve Hill Solar Park Order 2020, Paragraph 12: Construction traffic management plan

Extent: E+W+S+N.I.

(1) No phase of the authorised development may commence until written details of a construction traffic management plan (which must accord with the outline construction traffic management plan) for that phase has been submitted to and approved by the relevant planning authority in consultation with the relevant highway authority.
(2) The construction traffic management plan must be implemented as approved.

---