  "url": "https://openlegislation.uk/cleve-hill-solar-park-order-2020/schedule-1/paragraph-15",
  "json_url": "https://openlegislation.uk/cleve-hill-solar-park-order-2020/schedule-1/paragraph-15.json",
  "legislation": "uksi/2020/547",
  "legislation_title": "The Cleve Hill Solar Park Order 2020",
  "legislation_url": "https://openlegislation.uk/cleve-hill-solar-park-order-2020",
  "path": "schedule/1/paragraph/15",
  "kind": "paragraph",
  "number": "15",
  "heading": "Operational noise",
  "text": "(1) No phase of the authorised development may commence until an operational noise assessment containing details of how the design of the authorised development has incorporated mitigation to ensure the operational noise rating levels as set out in the environmental statement are to be complied with for that phase has been submitted to and approved by the relevant local planning authority.\n(2) The design as described in the operational noise assessment must be implemented as approved.",
  "extent": "E+W+S+N.I.",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 Pt. 2 para. 15 in force at 19.6.2020, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2020/547/schedule/1/paragraph/15",
    "retrieved_at": "2026-10-28T22:29:58.694290+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}