# The Cleve Hill Solar Park Order 2020, Paragraph 1: Primary objective

Extent: E+W+S+N.I.

(1) The primary objective of these arbitration rules is to achieve a fair, impartial, final and binding award on the substantive difference between the parties (save as to costs) within 4 months from the date the arbitrator is appointed pursuant to article 35 of this Order.
(2) The arbitration will be deemed to have commenced when a party (“the Claimant”) serves a written notice of arbitration on the other party (“the Respondent”).

---
Source: https://www.legislation.gov.uk/uksi/2020/547/schedule/9/paragraph/1 (the official version)