# The Clocaenog Forest Wind Farm Order 2014, Paragraph 10: Highways

Extent: E+W

No wind turbine parts may be delivered to the site before detailed plans and drawings in respect of Work No. 4A or 4B (whichever is decided on by the undertaker) have been submitted to and approved by the relevant planning authority and such works have been constructed in accordance with the plans and drawings so approved.

---
Source: https://www.legislation.gov.uk/uksi/2014/2441/schedule/1/paragraph/10 (the official version)
Page: https://openlegislation.uk/clocaenog-forest-wind-farm-order-2014/schedule-1/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.