# The Clocaenog Forest Wind Farm Order 2014, Paragraph 12


The authorised development may not commence until following consultation with the Department for Transport of the Welsh Government and any relevant highway authority details of the reinstatement of the public highway and its associated street furniture following completion of the construction of the authorised development have been submitted to and approved by the relevant planning authority. The reinstatement works are to be implemented in accordance with the approved details.

---