  "number": "27",
  "heading": "Accumulation and deposits",
  "text": "(1) No authorised development may commence until, following consultation with NRW, a written scheme for the management of any accumulations and deposits has been submitted to and approved by the relevant planning authority.\n(2) The approved scheme for the management of accumulations and deposits is to be implemented before and maintained during the construction, operation and decommissioning of the authorised development.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 Pt. 3 para. 27 in force at 2.10.2014, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2014/2441/schedule/1/paragraph/27",
    "retrieved_at": "2026-10-29T00:02:54.990189+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}