  "heading": "Authorised development",
  "text": "A wind energy electricity generating station with an installed capacity of between 64 and 96MW comprising a nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act consisting of—\nWork No. 1 – Up to 32 wind turbines each sited on concrete foundations incorporating hardstanding for cranes, each turbine being fitted with rotating blades and having a height to blade tip of up to 145 metres and including external transformers located at the base of the turbine. The wind turbines comprising Work No. 1 will be situated at the following locations—\nWind turbine number\nGrid reference\nEasting\nNorthing\nWT 1\n301118\n358328\nWT 2\n301550\n358106\nWT 3\n301063\n357801\nWT 4\n300021\n357651\nWT 5\n300510\n357483\nWT 6\n301065\n357256\nWT 7\n300449\n357030\nWT 8\n301282\n356957\nWT 9\n300057\n356694\nWT 10\n301308\n356533\nWT 11\n301151\n356100\nWT 12\n300741\n355620\nWT 13\n301320\n355593\nWT 14\n300957\n355275\nWT 15\n301512\n355170\nWT 16\n301081\n354833\nWT 17\n301599\n354551\nWT 18\n301885\n354174\nWT 19\n302153\n353716\nWT 20\n301561\n353647\nWT 21\n300770\n353343\nWT 22\n301297\n353291\nWT 23\n302358\n353159\nWT 24\n300610\n352531\nWT 25\n301716\n352540\nWT 26\n301193\n352528\nWT 27\n302724\n352076\nWT 28\n300752\n352025\nWT 29\n301198\n351850\nWT 30\n301382\n351501\nWT 31\n300880\n350721\nWT 32\n301232\n350505\nIn Work No. 1, references to the locations of a wind turbine are references to the centre point of that turbine.\nWork No. 2A – A series of electrical cables with a nominal voltage of 33 kilovolts together with a cable for the transmission of electronic communications buried beneath the surface of the ground along the general line of the tracks and roads comprised in Work No. 3 and connecting the wind turbines comprising Work No. 1 and the onsite electricity substation comprising Work No. 5A arranged in the following circuit routes—\nCable circuit route number\nCommencement point\nTermination point\n1\nSubstation forming Work No. 5A\nWT1\nWT1\nWT2\nWT2\nWT3\nWT3\nWT4\nWT4\nWT5\nWT5\nWT7\nWT7\nWT9\n2\nSubstation forming Work No. 5A\nWT6\nWT6\nWT8\nWT8\nWT10\nWT10\nWT11\nWT11\nWT12\nWT12\nWT13\nWT13\nWT14\n3\nSubstation forming Work No. 5A\nWT15\nWT15\nWT16\nWT16\nWT17\nWT17\nWT18\nWT18\nWT20\nWT20\nWT21\n4\nSubstation forming Work No. 5A\nWT19\nWT19\nWT22\nWT22\nWT23\nWT23\nWT24\nWT24\nWT26\nWT26\nWT28\n5\nSubstation forming Work No. 5A\nWT25\nWT25\nWT27\nWT27\nWT29\nWT29\nWT30\nWT30\nWT31\nWT31\nWT32\nWork No. 2B – A series of electrical cables with a nominal voltage of 33 kilovolts together with a cable for the transmission of electronic communications buried beneath the surface of the ground along the general line of the tracks and roads comprised in Work No. 3 and connecting the wind turbines comprising Work No. 1 and the onsite electricity substation comprising Work No. 5B arranged in the following circuit routes—\nCable circuit route number\nCommencement point\nTermination point\n1\nSubstation forming Work No. 5B\nWT24\nWT24\nWT26\nWT26\nWT28\nWT28\nWT30\nWT30\nWT31\nWT31\nWT32\n2\nSubstation forming Work No. 5B\nWT19\nWT19\nWT22\nWT22\nWT23\nWT23\nWT25\nWT25\nWT27\nWT27\nWT29\n3\nSubstation forming Work No. 5B\nWT15\nWT15\nWT16\nWT16\nWT17\nWT17\nWT18\nWT18\nWT20\nWT20\nWT21\n4\nSubstation forming Work No. 5B\nWT6\nWT6\nWT8\nWT8\nWT10\nWT10\nWT11\nWT11\nWT12\nWT12\nWT13\nWT13\nWT14\n5\nSubstation forming Work No. 5B\nWT1\nWT1\nWT2\nWT2\nWT3\nWT3\nWT4\nWT4\nWT5\nWT5\nWT7\nWT7\nWT9\nWork No. 3 – A series of new tracks, existing tracks subject to improvement and widening, public roads subject to widening and a series of turning heads located adjacent to tracks as described in the following tables—\nNew tracks\nAccess track no\nCommencement point\nTermination point\nEasting\nNorthing\nEasting\nNorthing\nN1\n301053\n354912\n301148\n354923\nN2\n301732\n353137\n301759\n353249\nN7\n300704\n357556\n301053\n357760\nN9\n300551\n354816\n300680\n354787\nN12\n301051\n357035\n301004\n356965\nN13\n300997\n356851\n301005\n356965\nN14\n301018\n355995\n301095\n355964\nN15\n300780\n355350\n300896\n355416\nN18\n301763\n352551\n301682\n352621\nN19\n301187\n352084\n301232\n351977\nN20\n300744\n358780\n300798\n358668\nN21\n299761\n357707\n299720\n357850\nN22\n300062\n357628\n299986\n357686\nN23\n301289\n352268\n301345\n352245\nN24\n301203\n352481\n301211\n352434\nN4\n301260\n351872\n301521\n351501\nN25\n300509\n357483\n300277\n357467\nN26\n300596\n357354\n300614\n357029\nN27\n301133\n355580\n300866\n355375\nN28\n300784\n355332\n300534\n355065\nNew spur tracks\nAccess track no\nCommencement point\nTermination point\nEasting\nNorthing\nEasting\nNorthing\nS1\n301062\n358319\n301118\n358328\nS2\n301515\n358109\n301549\n358107\nS3\n301063\n357801\n301069\n357772\nS4\n300030\n357651\n300021\n357651\nS5\n300740\n357556\n300509\n357483\nS6\n301122\n357097\n301065\n357256\nS7\n300529\n356984\n300449\n357030\nS8\n301122\n357097\n301282\n356957\nS9\n300069\n356708\n300057\n356694\nS10\n301343\n356415\n301308\n356533\nS11\n301151\n356100\n301108\n355973\nS12\n300741\n355620\n300999\n355802\nS13\n301084\n355554\n301320\n355593\nS14\n300834\n355306\n300957\n355275\nS15\n301438\n355078\n301511\n355170\nS16\n301081\n354834\n301063\n354899\nS17\n301554\n354556\n301599\n354551\nS18\n301885\n354174\n301845\n354063\nS19\n301875\n353692\n302153\n353716\nS20\n301475\n353692\n301561\n353647\nS21\n300739\n353256\n300770\n353343\nS22\n301295\n353259\n301297\n353291\nS23\n302199\n353104\n302358\n353159\nS24\n300686\n352482\n300610\n352531\nS25\n301716\n352540\n301717\n352591\nS26\n301268\n352594\n301193\n352528\nS27\n302263\n351904\n302723\n352077\nS28\n300841\n352162\n300841\n352161\nS29\n301235\n351963\n301198\n351850\nS30\n301378\n351623\n301382\n351501\nS31\n301678\n350884\n300880\n350721\nS32\n301301\n350647\n301232\n350505\nSMM1\n299997\n356584\n299893\n356575\nSMM2\n300653\n351909\n300734\n351823\nExisting tracks subject to improvement and widening\nAccess track no\nCommencement point\nTermination point\nEasting\nNorthing\nEasting\nNorthing\nE1\n300890\n358336\n301051\n358313\nE2\n301051\n358313\n301375\n358861\nE5\n300649\n357389\n300023\n357656\nE6\n300614\n357029\n301001\n356966\nE7\n301001\n356966\n301122\n357097\nE8\n300624\n357064\n300325\n356915\nE9\n300330\n356917\n300224\n356913\nE10\n300224\n356913\n299997\n356584\nE11\n300781\n355353\n301103\n355969\nE12\n301103\n355970\n301343\n356415\nE13\n300570\n355106\n300609\n354651\nE14\n300604\n354689\n300695\n354798\nE15\n300695\n354798\n301053\n354912\nE16\n301148\n354922\n301442\n355081\nE17\n300609\n354649\n300728\n354115\nE18\n300706\n354150\n301554\n354556\nE19\n300729\n354114\n300659\n353686\nE20\n300658\n353686\n300511\n353164\nE21\n300510\n353161\n301845\n354063\nE22\n300510\n353161\n300777\n353046\nE23\n300775\n353045\n301194\n353212\nE24\n301197\n353212\n301877\n353693\nE25\n301196\n353212\n301707\n353255\nE26\n301709\n353255\n301829\n353240\nE27\n301833\n353239\n301908\n353231\nE28\n301895\n353232\n302199\n353104\nE29\n301731\n353137\n301309\n352690\nE30\n301310\n352692\n300686\n352482\nE31\n301311\n352692\n301191\n352457\nE32\n301191\n352456\n301307\n352227\nE33\n301191\n352457\n300653\n351909\nE34\n301307\n352227\n301408\n352268\nE35\n301408\n352268\n301552\n352563\nE36\n301549\n352557\n301681\n352621\nE37\n301849\n352476\n302224\n352055\nE38\n302225\n352055\n302263\n351904\nE40\n301307\n352227\n301187\n352084\nE41\n301233\n351978\n301259\n351861\nE43\n301521\n351501\n301693\n351263\nE46\n301678\n350885\n301300\n350648\nE50\n300997\n356851\n301018\n355898\nE51\n301047\n354916\n301151\n354924\nE53\n301053\n357760\n301515\n358109\nE54\n301682\n352621\n301848\n352477\nE56\n301678\n350885\n301693\n351263\nE57\n300023\n357656\n299761\n357707\nPublic roads subject to widening\nPublic road no\nCommencement point\nTermination point\nEasting\nNorthing\nEasting\nNorthing\nPR1\n300744\n358778\n300624\n357351\nPR2\n300624\n357351\n300634\n357032\nPR3\n301085\n355555\n300571\n355108\nPR5\n302454\n350166\n301749\n351092\nTurning Heads\nGrid reference\nTurning head number\nEasting\nNorthing\nTH1 (at T3)\n301166\n357866\nTH2 (between T7 and T9)\n300226\n356920\nTH3 (at T10)\n301344\n356350\nTH4 (at T13\n301221\n355570\nTH5 (at T15)\n301436\n355089\nTH6 (at T17)\n301501\n354506\nTH7 (at T18)\n301833\n354061\nTH8 (at T24)\n300672\n352492\nTH9 (at T25)\n301854\n352484\nTH10 (at T28)\n300817\n352143\nTH11 (at T30)\n301367\n351613\nTH12 (at T31)\n300989\n350791\nTH13 (at T32)\n301314\n350614\nIn constructing Work No. 3 the undertaker may—\n(a)provide temporary passing places for construction vehicles at any location along the line of the work shown on the works plan within the limits of deviation for Work No. 3; and\n(b)construct culverts to carry any watercourse under Work No. 3 and extend or replace any existing culvert to carry such a watercourse.\nWork No. 4A – A widening of part of the of the unnamed public road shown as PR1 at X on Works Plan 1 to provide construction, maintenance and emergency site access commencing at Ordnance Survey National Grid Reference Point SJ0074458778.\nWork No. 4B – A widening of part of the of the unnamed public road shown as PR5 at X on Works Plan 7 to provide construction, maintenance and emergency site access commencing at Ordnance Survey National Grid Reference Point SJ0245550165.\nWork No. 5A – An onsite electricity substation comprising an enclosed area of hardstanding of 4080 square metres located at Ordnance Survey National Grid Reference Point SJ0136958813 and including a control building to house switch gear and control equipment.\nWork No. 5B – An onsite electricity substation comprising an enclosed area of hardstanding of 4080 square metres located at Ordnance Survey National Grid Reference Point SJ0215150472 and including a control building to house switch gear and control equipment.\nWork No. 6 – A meteorological mast for the purpose of monitoring and recording wind speed and direction as well as air temperature, having a height of 100 metres and sited on an area of hardstanding of 900 square metres and located at Ordnance Survey National Grid Reference Point SH9989356575. Work No. 6 includes a cable for the transmission of electronic communications from wind turbine No. 9 comprised in Work No. 1 along the line of existing track No. E10 and new spur track No. SMM1 comprised in Work No. 3.\nWork No. 7 – A meteorological mast for the purpose of monitoring and recording wind speed and direction as well as air temperature, having a height of 100 metres and sited on an area of hardstanding of 900 square metres and located at Ordnance Survey National Grid Reference Point SJ0073551823. Work No. 7 includes a cable for the transmission of electronic communications along the line of existing track No. E33 from its junction with new spur track No. S28 and new spur track No. SMM2 comprised in Work No. 3.\nWork No. 8 – A temporary civil construction compound comprising an enclosed area of hardstanding of 2500 square metres located at Ordnance Survey National Grid Reference Point SJ0095558354 and including a temporary office and staff welfare building together with an area for the storage of materials for use in the construction of the authorised development.\nWork No. 9 – A temporary civil construction compound comprising an enclosed area of hardstanding of 2500 square metres located at Ordnance Survey National Grid Reference Point SJ0178451133 and including a temporary office and staff welfare building together with an area for the storage of materials for use in the construction of the authorised development.\nWork No. 10 – A borrow pit for the extraction of stone to be used in the construction of the authorised development, having an area of 39,200 square metres and a depth of up to 18 metres located at Ordnance Survey National Grid Reference Point SJ0189157562.\nWork No. 11 – A borrow pit for the extraction of stone to be used in the construction of the authorised development, having an area of approximately 13,600 square metres and a depth of up to 16 metres located at Ordnance Survey National Grid Reference Point SJ0246654106.\nWork No. 12 – A borrow pit for the extraction of stone to be used in the construction of the authorised development, having an area of approximately 18,300 square metres and a depth of up to 20 metres located at Ordnance Survey National Grid Reference Point SJ0185151493.\nWork No. 13 – A borrow pit for the extraction of stone to be used in the construction of the authorised development, having an area of approximately 11,300 square metres and a depth of up to 19 metres located at Ordnance Survey National Grid Reference Point SJ0078050630.\nWork No. 14A – A temporary electrical compound comprising an enclosed area of hardstanding of 2500 square metres located adjacent to the onsite electricity substation forming Work No. 5A at Ordnance Survey National Grid Reference Point SJ0131558784.\nWork No. 14B – A temporary electrical compound comprising an enclosed area of hardstanding of 2500 square metres located adjacent to the onsite electricity substation forming Work No. 5B at Ordnance Survey National Grid Reference Point SJ0219750429.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 Pt. 1 in force at 2.10.2014, see art. 1"
    },
    {
      "type": "F",
      "label": "F1",
      "text": "Words in Sch. 1 Pt. 1 substituted (8.12.2017) by The Clocaenog Forest Wind Farm (Amendment) Order 2017 (S.I. 2017/1197), arts. 1, 5(1)"
    },
    {
      "type": "F",
      "label": "F2",
      "text": "Word in Sch. 1 Pt. 1 table entitled \"New tracks\" substituted (8.12.2017) by The Clocaenog Forest Wind Farm (Amendment) Order 2017 (S.I. 2017/1197), arts. 1, 5(3)(a)(i)"
    },
    {
      "type": "F",
      "label": "F3",
      "text": "Word in Sch. 1 Pt. 1 table entitled \"New tracks\" substituted (8.12.2017) by The Clocaenog Forest Wind Farm (Amendment) Order 2017 (S.I. 2017/1197), arts. 1, 5(3)(a)(ii)"
    },
    {
      "type": "F",
      "label": "F4",
      "text": "Words in Sch. 1 Pt. 1 table entitled \"New tracks\" inserted (8.12.2017) by The Clocaenog Forest Wind Farm (Amendment) Order 2017 (S.I. 2017/1197), arts. 1, 5(3)(b)"
    },
    {
      "type": "F",
      "label": "F5",
      "text": "Word in Sch. 1 Pt. 1 table entitled \"Existing tracks subject to improvement and widening\" substituted (8.12.2017) by The Clocaenog Forest Wind Farm (Amendment) Order 2017 (S.I. 2017/1197), arts. 1, 5(4)(a)"
    },
    {
      "type": "F",
      "label": "F6",
      "text": "Word in Sch. 1 Pt. 1 table entitled \"Existing tracks subject to improvement and widening\" substituted (8.12.2017) by The Clocaenog Forest Wind Farm (Amendment) Order 2017 (S.I. 2017/1197), arts. 1, 5(4)(b)"
    },
    {
      "type": "F",
      "label": "F7",
      "text": "Sch. 1 Pt. 1 table inserted (8.12.2017) by The Clocaenog Forest Wind Farm (Amendment) Order 2017 (S.I. 2017/1197), arts. 1, 5(5)"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2014/2441/schedule/1/part/1",
    "retrieved_at": "2026-10-29T00:02:54.990189+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}