# The Coal Mining Subsidence (Land Drainage) Regulations 1994, Regulation 6: Variation of remedial measures


(1) Where, after remedial measures have been agreed or determined in the manner provided by these Regulations, those measures are varied either—
(i) by agreement between the responsible person and the appropriate drainage authority,
(ii) by a further determination made by the Ministers under regulation 3(5) above, or
(iii) by an award made under section 22 of the Arbitration Act 1950 or an order or award made under section 1 of the Arbitration Act 1979,
every such variation shall be deemed to revoke any notice given under regulation 5(1) above, and the responsible person shall give a further notice under that regulation.
(2) Nothing in this regulation shall relieve the responsible person from liability to make any payment to the appropriate drainage authority in respect of such measures as have been carried out by that authority before any such variation.

---
Source: https://www.legislation.gov.uk/uksi/1994/3064/regulation/6 (the official version)
Page: https://openlegislation.uk/coal-mining-subsidence-land-drainage-regulations-1994/regulation-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.