# The Construction (Design and Management) Regulations 2015, Regulation 7: Application to domestic clients


(1) Where the client is a domestic client the duties in regulations 4(1) to (7) and 6 must be carried out by—
(a) the contractor for a project where there is only one contractor;
(b) the principal contractor for a project where there is more than one contractor; or
(c) the principal designer where there is a written agreement that the principal designer will fulfil those duties.
(2) If a domestic client fails to make the appointments required by regulation 5—
(a) the designer in control of the pre-construction phase of the project is the principal designer;
(b) the contractor in control of the construction phase of the project is the principal contractor.
(3) Regulation 5(3) and (4) does not apply to a domestic client.

---
Source: https://www.legislation.gov.uk/uksi/2015/51/regulation/7 (the official version)
Page: https://openlegislation.uk/construction-design-and-management-regulations-2015/regulation-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.