# The Construction (Design and Management) Regulations (Northern Ireland) 2016, Paragraph 7: Projects with only one contractor


Where a relevant project has only one contractor and the construction phase has started, the contractor shall draw up a construction phase plan, or make arrangements for a construction phase plan to be drawn up, under regulation 15(5) and (6) as soon as is practicable after 1st August 2016 and the requirement that the plan shall be drawn up prior to setting up a construction site is disapplied.

---