# The Contracts for Difference (Allocation) Regulations 2014, Regulation 40: Delay after completion of contract allocation processes

Extent: E+W+S

(1) Where the delay period has expired—
(a) a proceed notice or a re-run notice must not be given; and
(b) the delivery body must not re-run part only of the contract allocation process.
(2) Where paragraph (1) applies the delivery body must—
(a) re-run the contract allocation process;
(b) comply with regulation 34(2) to (6); and
(c) after completion of the re-run, comply with regulation 35 and Chapter 4 of this Part.
(3) In this regulation, “delay period” means—
(a) where a variation notice was not required to be given when the contract allocation process commenced, a period of more than 5 months has expired since the application closing date; or
(b) where a variation notice was required to be given when the contract allocation process commenced, a period of more than 5 months has expired since the date on which the variation notice was required to be given.
(4) The contract allocation framework for the allocation round may provide for a period other than “5 months” stated in paragraph (3)(a) or (b) and where such other period is provided, “delay period” has effect with that modification.

---
Source: https://www.legislation.gov.uk/uksi/2014/2011/regulation/40 (the official version)