Regulation 16 Amendment to regulation 51
In regulation 51 (successful applications determined by the Authority)—
after paragraph (1) insert—
“(1A)Paragraph (1B) applies where the delivery body—
(a)receives a notice from the Authority in accordance with regulation 46(3) that states the determination of the Authority is that an applicant is a qualifying applicant; and
(b)has not given a proceed notice under regulation 37(1)(b)(i) in respect of the most recent run of the allocation process for the allocation round.
(1B)Where this paragraph applies, the delivery body must—
(a)re-run the allocation process; and
(b)after completion of the re-run, comply with regulation 35.”;
in paragraph (2), after “Chapter 4 or 5 of Part 5” insert “or paragraph (1B)”;
in paragraph (3), after “is a successful application” insert “in accordance with the allocation framework for the allocation round”;
in paragraph (6)—
in sub-paragraph (a), for “the information provided in compliance with paragraph 3(a)(iv) of Schedule 1 (“the target dates”)” substitute “target dates”;
in sub-paragraphs (a) to (c), for “varied” substitute “delayed”; and
in sub-paragraph (b), for “vary” substitute “delay”;
in paragraph (7), for “except any flexible bid” substitute “including any flexible bid”;
for paragraph (10) substitute—
“(10)In paragraph (7), “flexible bid” means a bid, where it is permitted under the allocation framework, in which the applicant specifies—
(a)a strike price;
(b)the first delivery year as a year the same as or after the first delivery year set out in the applicant’s application;
(c)a target commissioning date as a date on or after the target commissioning date provided by the applicant with the applicant’s application; and
(d)the amount of electricity to be generated as an amount which is no greater than the amount set out in the applicant’s application.”.