# The Control of Noise (Code of Practice for Construction and Open Sites) (England) Order 2015, Article 1: Citation, commencement, extent and application

Extent: E+W

(1) This order may be cited as the Control of Noise (Code of Practice for Construction and Open Sites) (England) Order 2015 and comes into force on 6th April 2015.
(2) This Order extends to England and Wales but applies in England only.

---
Source: https://www.legislation.gov.uk/uksi/2015/227/article/1 (the official version)
Page: https://openlegislation.uk/control-of-noise-code-of-practice-for-construction-and-open-sites-england-order-2015/article-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.