OpenLegislation

Regulation 10 Notification requirements

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

(1)

A person who proposes to have custody or control of any relevant substance which is to be kept or stored on a farm in a silo, slurry storage system or, as the case may be, fuel storage area constructed, substantially enlarged or substantially reconstructed on or after lst September 1991 shall serve notice on the river purification authority specifying the type of structure to be used and its location at least 14 days before it is to be used for such purpose.

(2)

A person who intends to make silage in 1991 by the method described in regulation 6(1) shall give notice of such intention to the river purification authority before 1st May 1991.