# The Cornwall Council (A30 Temple to Higher Carblake Improvement) Order 2015, Paragraph 9: Building and construction materials – highways

Extent: E+W+S

(1) No part of the authorised development is to commence until written details of the materials to be used for the surfacing of the new highway have been submitted to and approved by the local planning authority.
(2) The details submitted under sub-paragraph (1) must include provision for the use of low noise road surfacing materials on the highway.
(3) The authorised development must be carried out using the materials approved under sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2015/147/schedule/2/paragraph/9 (the official version)