# The Corporate Insolvency and Governance Act 2020 (Coronavirus) (Early Termination of Part 2 of Schedule 8) Regulations (Northern Ireland) 2022, Regulation 3: Saving provision


Despite regulation 2, paragraphs 8 to 11 of Schedule 8 to the Corporate Insolvency and Governance Act 2020 continue to have effect in relation to a moratorium if-
(a) the moratorium came into force, or
(b) in the case of a moratorium that came into force as a result of an application under either Article 13BA or 13BB of the Insolvency (Northern Ireland) Order 1989, the application was made,
before 14 October 2020.

---
Source: https://www.legislation.gov.uk/nisr/2022/4/regulation/3 (the official version)
Page: https://openlegislation.uk/corporate-insolvency-and-governance-act-2020-coronavirus-early-termination-of-part-2-of-schedule-8-regulations-northern-ireland-2022/regulation-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.