# The Cory Decarbonisation Project Order 2025, Paragraph 11: Sediment sampling

Extent: E+W

(1) If the undertaker considers that sediment sampling is required to demonstrate the appropriateness of a methodology to be included in a method statement relating to construction licensed activities or maintenance dredging submitted to the MMO for approval under condition 10, prior to submitting that construction method statement to the MMO, the undertaker must submit a sediment sampling plan for approval by the MMO.
(2) Any sediment sampling required under sub-paragraph (1) must be carried out in accordance with the approved sediment sampling plan, unless otherwise agreed in writing by the MMO.

---