  "heading": "Piling",
  "text": "Where a licensed activity involves percussive piling the undertaker must commence piling activities using soft-start techniques for at least 20 minutes to ensure an incremental increase in pile power until full operational power is achieved. Should piling cease for at least 20 minutes the soft-start procedures must be repeated.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 11 para. 13 in force at 27.11.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1227/schedule/11/paragraph/13",
    "retrieved_at": "2026-10-28T21:09:19.424447+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}