# The Cory Decarbonisation Project Order 2025, Paragraph 19: Disposal

Extent: E+W

The undertaker must inform the MMO of the location and quantities of material disposed of each month under this licence. This information must be submitted to the MMO by 15th February each year for the months August to January inclusive, and by 15th August each year for the months February to July inclusive.

---
Source: https://www.legislation.gov.uk/uksi/2025/1227/schedule/11/paragraph/19 (the official version)
Page: https://openlegislation.uk/cory-decarbonisation-project-order-2025/schedule-11/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.