# The Cory Decarbonisation Project Order 2025, Paragraph 25: Variations of approvals of Part 2 Conditions

Extent: E+W

(1) With respect to any condition under Part 2 which requires a licensed activity to be carried out in accordance with any plans, protocols or statements approved under this licence, the approved details, plan or scheme are to be taken to include any amendments that may subsequently be approved in writing by the MMO.
(2) Subsequent to the first approval of those plans, protocols or statements, any amendments will only be approved by the MMO if the undertaker has demonstrated to the reasonable satisfaction of the MMO that the subject matter of the relevant amendments do not give rise to any materially new or materially different environmental effects that are worse than those identified in the environmental statement.

---
Source: https://www.legislation.gov.uk/uksi/2025/1227/schedule/11/paragraph/25 (the official version)
Page: https://openlegislation.uk/cory-decarbonisation-project-order-2025/schedule-11/paragraph-25
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.