# The Cory Decarbonisation Project Order 2025, Paragraph 116

Extent: E+W

Where in consequence of the proposed construction or maintenance of any part of the authorised development, the undertaker or REPL requires the removal of apparatus or REPL makes requirements for the protection or alteration of apparatus, the undertaker shall use its reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution and maintenance of the authorised development and taking into account the need to ensure the safe and efficient operation of REPL’s undertaking and REPL shall use its reasonable endeavours to co-operate with the undertaker for that purpose.

---