# The Cory Decarbonisation Project Order 2025, Paragraph 129

Extent: E+W

If in consequence of any agreement reached or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable each RRRL Entity to maintain or use the apparatus no less effectively than was possible before such obstruction.

---
Source: https://www.legislation.gov.uk/uksi/2025/1227/schedule/12/paragraph/129 (the official version)
Page: https://openlegislation.uk/cory-decarbonisation-project-order-2025/schedule-12/paragraph-129
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.