# The Cory Decarbonisation Project Order 2025, Paragraph 29: The Thames Flood Acts works

Extent: E+W

Nothing in Article 7 prevents the Agency serving a notice on the undertaker under the Thames Flood Acts requiring works to, or financial contributions towards, raising the crest levels of flood defences or reinforcement to flood defences to improve the standard of flood protection and the undertaker being required to comply with any such notice pursuant to the Thames Flood Acts.

---
Source: https://www.legislation.gov.uk/uksi/2025/1227/schedule/12/paragraph/29 (the official version)
Page: https://openlegislation.uk/cory-decarbonisation-project-order-2025/schedule-12/paragraph-29
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.