  "url": "https://openlegislation.uk/cory-decarbonisation-project-order-2025/schedule-12/paragraph-78",
  "json_url": "https://openlegislation.uk/cory-decarbonisation-project-order-2025/schedule-12/paragraph-78.json",
  "legislation": "uksi/2025/1227",
  "legislation_title": "The Cory Decarbonisation Project Order 2025",
  "legislation_url": "https://openlegislation.uk/cory-decarbonisation-project-order-2025",
  "path": "schedule/12/paragraph/78",
  "kind": "paragraph",
  "number": "78",
  "heading": "Disputes",
  "text": "Subject to any protocol agreed in writing by the parties, any dispute arising between the undertaker and the PLA under this Part of this Schedule is to be determined by arbitration as provided in article 49 (arbitration).",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 12 para. 78 in force at 27.11.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1227/schedule/12/paragraph/78",
    "retrieved_at": "2026-10-28T21:09:19.424447+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}