{
  "url": "https://openlegislation.uk/cory-decarbonisation-project-order-2025/schedule-12/paragraph-99",
  "json_url": "https://openlegislation.uk/cory-decarbonisation-project-order-2025/schedule-12/paragraph-99.json",
  "legislation": "uksi/2025/1227",
  "legislation_title": "The Cory Decarbonisation Project Order 2025",
  "legislation_url": "https://openlegislation.uk/cory-decarbonisation-project-order-2025",
  "path": "schedule/12/paragraph/99",
  "kind": "paragraph",
  "number": "99",
  "heading": "Retained apparatus: protection of SGN",
  "text": "(1) Not less than 56 days before the commencement of any specified works, the undertaker must where reasonably required by SGN submit to SGN a plan and, a ground monitoring scheme in respect of those works.\n(2) In relation to works which will or may be situated on, over, under or within (a) ten metres measured in any direction of any apparatus, or (b) involve embankment works within ten metres of any apparatus, the plan to be submitted where reasonably required to SGN under sub-paragraph (1) must include a method statement and describe—\n(a) the exact position of the works;\n(b) the level at which these are proposed to be constructed or renewed;\n(c) the manner of their construction or renewal including details of excavation, positioning of plant etc.;\n(d) the position of all apparatus;\n(e) by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus; and\n(f) any intended maintenance regimes.\n(3) The undertaker must not commence any works to which sub-paragraphs (1) and (2) apply until SGN has given written approval of the plan so submitted.\n(4) Any approval of SGN required under sub-paragraph (3)—\n(a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraph (5) or (7); and\n(b) must not be unreasonably withheld or delayed.\n(5) In relation to any work to which sub-paragraphs (1) and/or (2) apply, SGN may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing apparatus against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.\n(6) Works to which this paragraph applies must only be executed in accordance with the plan, submitted under sub-paragraphs (1) and (2) or as relevant sub-paragraph (4), as approved or as amended from time to time by agreement between the undertaker and SGN and in accordance with all conditions imposed under sub-paragraph (4)(a), and SGN will be entitled to watch and inspect the execution of those works.\n(7) Where SGN requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to SGN’s satisfaction prior to the commencement of any authorised works (or any relevant part thereof) for which protective works are required and SGN must give 45 days’ notice of such works from the date of submission of a plan pursuant to this paragraph (except in an emergency).\n(8) If SGN, in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 91 to 93 and 96 to 98 apply as if the removal of the apparatus had been required by the undertaker under paragraph 97(2).\n(9) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the authorised works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph will apply to and in respect of the new plan.\n(10) The undertaker is not required to comply with sub-paragraph (1) where it needs to carry out emergency works as defined in the 1991 Act, but in that case it must give to SGN notice as soon as is reasonably practicable and a plan of those works and must comply with—\n(a) the conditions imposed under sub-paragraph (4)(a) insofar as is reasonably practicable in the circumstances; and\n(b) sub-paragraph (11) at all times.\n(11) As soon as reasonably practicable after any ground subsidence event which is known to or may have affected apparatus attributable to the authorised development the undertaker must implement an appropriate ground mitigation scheme save that SGN retains the right to carry out any further necessary protective works for the safeguarding of its apparatus and can recover any such costs in line with paragraph 100.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 12 para. 99 in force at 27.11.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1227/schedule/12/paragraph/99",
    "retrieved_at": "2026-10-28T21:09:19.424447+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}