# The Cory Decarbonisation Project Order 2025, Schedule 13: DOCUMENTS AND PLANS TO BE CERTIFIED

Extent: E+W

(1)
Document name
(2)
Document reference
(3)
Revision number
(4)
Date
access and rights of way plan
2.4
P03
September 2024
book of reference
4.3
Rev H
May 2025
design principles and design code
5.7
Rev E
March 2025
environmental statement
environmental statement 6.1 (excluding chapters 2, 4, 5, 7, 8, 9, 11, 14, 19, 21 and 22)
Rev A
March 2024
environmental statement 6.1 Chapter 2
Rev B
April 2025
environmental statement 6.1 Chapter 4
Rev B
April 2025
environmental statement 6.1 Chapter 5
Rev B
April 2025
environmental statement 6.1 Chapter 7
Rev B
April 2025
environmental statement 6.1 Chapter 8
Rev B
April 2025
environmental statement 6.1 Chapter 9
Rev B
April 2025
environmental statement 6.1 Chapter 11
Rev B
April 2025
environmental statement 6.1 Chapter 14
Rev B
April 2025
environmental statement 6.1 Chapter 19
Rev B
April 2025
environmental statement 6.1 Chapter 21
Rev B
April 2025
environmental statement 6.1 Chapter 22
Rev B
April 2025
environmental statement 6.2 (excluding figures 3.3, 7.4, 7.10 and 11.2)
Rev A
March 2024
environmental statement 6.2 (figure 3.3)
Rev B
September 2024
environmental statement 6.2 (figure 7.4)
Rev B
April 2025
environmental statement 6.2 (figure 7.10)
Rev B
April 2025
environmental statement 6.2 (figure 11.2)
Rev B
April 2025
environmental statement 6.3 (excluding appendices 2.1, 4.2, 5.2, 5.3, 5.4, 7.8, 7.9, 10.4, 11.1, 11.2, 11.4 and 19.1)
Rev A
March 2024
environmental statement 6.3 (appendix 2.1)
Rev C
February 2025
environmental statement 6.3 (appendix 4.2)
Rev B
April 2025
environmental statement 6.3 (appendix 5.2)
Rev B
April 2025
environmental statement 6.3 (appendix 5.3)
Rev B
April 2025
environmental statement 6.3 (appendix 5.4)
Rev B
April 2025
environmental statement 6.3 (appendix 7.8)
Rev B
April 2025
environmental statement 6.3 (appendix 7.9)
Rev B
April 2025
environmental statement 6.3 (appendix 11.1)
Rev B
April 2025
environmental statement 6.3 (appendix 11.2)
Rev B
September 2024
environmental statement 6.3 (appendix 11.4)
Rev B
April 2025
environmental statement 6.3 (appendix 19.1)
Rev E
April 2025
environmental statement 6.3 (appendix 10.4)
Rev B
January 2025
extended crossness local nature reserve plan
2.9
P04
January 2025
flood risk assessment
6.3 Appendix 11.2
Rev B
September 2024
framework construction traffic management plan
7.7
Rev E
March 2025
land plans
2.2
P05
February 2025
mitigation schedule
7.8
Rev B
November 2024
outline landscape, biodiversity, access and recreation delivery strategy
7.9
Rev H
October 2025
outline code of construction practice
7.4
Rev E
March 2025
outline drainage strategy
7.2
Rev C
April 2025
outline emergency preparedness and response plan
7.11
Rev C
April 2025
outline lighting strategy
7.3
Rev B
March 2025
outline site waste management plan
7.10
Rev B
April 2025
outline skills and employment plan
9.15
Rev A
December 2024
preliminary navigation risk assessment
6.3 Appendix 19.1
Rev E
April 2025
traffic regulation measures plan
2.6
P03
September 2024
works plans
2.3
P08
April 2025

---
Source: https://www.legislation.gov.uk/uksi/2025/1227/schedule/13 (the official version)
Page: https://openlegislation.uk/cory-decarbonisation-project-order-2025/schedule-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.