# The Cory Decarbonisation Project Order 2025, Paragraph 1: Commencing an arbitration

Extent: E+W

(1) The primary objective of these arbitration rules is to achieve a fair, impartial, final and binding award on the substantive difference between the parties (save as to costs) within four months from the date the arbitrator is appointed pursuant to article 49 of this Order (arbitration).
(2) The arbitration is deemed to have commenced when a party (“the claimant”) serves a written notice of arbitration on the other party (“the respondent”).

---
Source: https://www.legislation.gov.uk/uksi/2025/1227/schedule/15/paragraph/1 (the official version)