  "text": "(1) No part of the authorised development may be commenced until the undertaker has submitted a heat strategy to the relevant planning authority for its written approval.\n(2) The heat strategy submitted under sub-paragraph (1) must—\n(a) provide an explanation of how the heat to be produced as a result of the authorised development, Riverside 1 and Riverside 2 could be captured and exported off-site;\n(b) set out the appropriate infrastructure that could be brought forward within the Order limits to enable the capture and export of heat from the site;\n(c) identify potential connection points for export of heat produced as a result of the authorised development, Riverside 1 and Riverside 2; and\n(d) provide an update on discussions with potential heat network providers.\n(3) The heat strategy submitted, and the relevant planning authority approval under sub-paragraph (1) must not require the undertaker to repeat actions already undertaken pursuant to—\n(a) requirement 24 (combined heat and power) of the REP Order;\n(b) any document produced pursuant to requirement 24 of the REP Order;\n(c) condition 31 of planning permission 16/02167/FUL relating to Riverside 1 issued by the London Borough of Bexley;\n(d) condition 31 of the consent issued under section 36C of the Electricity Act 1989 in respect of Riverside 1 dated 17 December 2021;\n(e) any condition of planning permission 22/00728/FUL issued by the London Borough of Bexley; and\n(f) any document produced pursuant to the requirements and conditions referred to in sub-paragraphs (a) to (e).\n(4) The heat strategy must be implemented as approved and such implementation does not constitute a breach of the documents, conditions and requirements referred to in sub-paragraphs (3)(a) to (3)(f).",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 25 in force at 27.11.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1227/schedule/2/paragraph/25",
    "retrieved_at": "2026-10-28T21:09:19.424447+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}