The Cottam Solar Project Order 2024 (“the Order”)f1, which granted development consent within the meaning of the Planning Act 2008 (“the Act”)f2, contains correctable errors within the meaning of paragraph 1 of Schedule 4 to the Act.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period (as defined in paragraph 1(6)(a) of Schedule 4 to the Act), the Secretary of State received a written request from the applicantf3 for the correction of errors in the Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed Lincolnshire County Council, Nottinghamshire County Council, West Lindsey District Council and Bassetlaw District Council as the relevant local planning authoritiesf4, that the request has been received.

The Secretary of State, in exercise of the powers conferred by section 119, and paragraphs 1(4) and 1(8) of Schedule 4 to the Act, makes the following Order—

Annotations

Footnotes

f1

S.I. 2024/943.

f2

2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20) and by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23). There are other amendments to the Act which are not relevant to this Order.

f3

As defined in paragraph 4 of Schedule 4 to the Act.

f4

As defined in paragraph 4 of Schedule 4 to the Act.