# The Cottam Solar Project Order 2024, Article 5: Power to maintain the authorised development

Extent: E+W

(1) The undertaker may at any time maintain the authorised development.
(2) This article only authorises the carrying out of maintenance works within the Order limits.
(3) This article does not authorise the carrying out of any works which are likely to give rise to any materially new or materially different effects that have not been assessed in the environmental statement.

---
Source: https://www.legislation.gov.uk/uksi/2024/943/article/5 (the official version)
Page: https://openlegislation.uk/cottam-solar-project-order-2024/article-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.