# The Cottam Solar Project Order 2024, Schedule 11: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Extent: E+W

(1)
Plot reference number shown on the land plan
(2)
Purpose for which temporary possession may be taken
01-031, 01-033, 01-034, 01-037, 01-038, 01‑039, 01-040, 02-048, 02-049, 02-050, 02‑051, 02-052, 02-053, 02-055, 02-056, 02‑067, 02-068, 02-069, 02-072, 02-073, 03‑082, 03-083, 03-085, 03-086, 03-087, 03‑094, 03-095, 04-100, 04-101, 04-102, 04‑105, 04-109, 04-110, 04-112, 05-122, 05‑127, 05-132, 05-138, 05-139, 06-144, 06‑150, 06-151, 08-173, 08-176, 09-187, 09‑189, 09-191, 09-193, 10-234, 10-236, 10‑237, 10-238, 10-242, 10-245, 11-254, 11‑256, 12-281, 14-284, 14-284a, 14-284b, 14‑284c, 14-284d, 14-284e, 14-284f, 14-284g, 14-285, 14-286, 14‑287, 14-290, 14-292, 14‑292a, 14-292b, 14-292d, 14-293, 14-293a, 14-294, 14-295, 14-296, 15-306, 15-308, 16‑325, 17-341, 18‑378, 18-380, 19-386, 19‑387, 19-388 and 19‑389.
Temporary use (including access) to facilitate the construction of Work Nos. 1 to 11.
01-035, 02-066, 02-075, 03-081, 03-088, 04‑106, 04-108, 04-113, 05-123, 05-131, 05‑137, 06-149, 08-185, 15-302, 16‑316, 16‑323, 17-332, 17-333, 17-334, 17-334a, 17‑342, 17-343, 17-344, 18-376, 19-401, 19‑402 and 20-403.
Temporary use (including access and compound) to facilitate the construction of Work No. 6.

---
Source: https://www.legislation.gov.uk/uksi/2024/943/schedule/11 (the official version)
Page: https://openlegislation.uk/cottam-solar-project-order-2024/schedule-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.