# The Cottam Solar Project Order 2024, Paragraph 148

Extent: E+W

To ensure its compliance with this Part, the undertaker must before carrying out any works or operations pursuant to this Order within Gate Burton Work No. 4B Area request up-to-date written confirmation from Gate Burton of the location of any apparatus or proposed apparatus.

---
Source: https://www.legislation.gov.uk/uksi/2024/943/schedule/15/paragraph/148 (the official version)
Page: https://openlegislation.uk/cottam-solar-project-order-2024/schedule-15/paragraph-148
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.