# The Cottam Solar Project Order 2024, Paragraph 48

Extent: E+W

Regardless of any provision in this Order or anything shown on the land plan, or contained in the book of reference, the undertaker may not acquire any apparatus, or override any easement or other interest of Northern Powergrid otherwise than by agreement with Northern Powergrid, such agreement not to be unreasonably withheld or delayed.

---
Source: https://www.legislation.gov.uk/uksi/2024/943/schedule/15/paragraph/48 (the official version)
Page: https://openlegislation.uk/cottam-solar-project-order-2024/schedule-15/paragraph-48
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

