# The Cottam Solar Project Order 2024, Paragraph 81: Protective works to buildings

Extent: E+W

The undertaker, in the case of the powers conferred by article 18 (protective works to buildings), may not exercise those powers so as to obstruct or render less convenient the access to any apparatus without the written consent of Anglian Water (such consent not to be unreasonably withheld or delayed).

---
Source: https://www.legislation.gov.uk/uksi/2024/943/schedule/15/paragraph/81 (the official version)
Page: https://openlegislation.uk/cottam-solar-project-order-2024/schedule-15/paragraph-81/enacted
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.