# The Cottam Solar Project Order 2024, Paragraph 18: Public rights of way

Extent: E+W

(1) No part of the authorised development may commence until a public rights of way management plan for any sections of public rights of way shown to be temporarily closed on the public rights of way plan for that part has been submitted to and approved by the relevant planning authority, or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.
(2) The public rights of way management plan must be substantially in accordance with the outline public rights of way management plan.
(3) Before approving the public rights of way management plan the relevant planning authority must consult with the relevant highway authority.
(4) The public rights of way management plan must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2024/943/schedule/2/paragraph/18 (the official version)
Page: https://openlegislation.uk/cottam-solar-project-order-2024/schedule-2/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.