# The Cottam Solar Project Order 2024, Paragraph 19: Soils management

Extent: E+W

(1) No part of the authorised development may commence until a soil management plan for that part has been submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple planning authorities, each of the relevant planning authorities.
(2) The soil management plan must be substantially in accordance with the outline soil management plan.
(3) The soil management plan must be implemented as approved.

---