# The Cottam Solar Project Order 2024, Part 2: TEMPORARY PROHIBITION OR RESTRICTION OF PUBLIC RIGHTS OF WAY WITH DIVERSION

Extent: E+W

(1)
Area
(2)
Public right of way
(3)
Measure
District of West Lindsey
Approximately 1423 metres of Footpath reference 2i Pilh/20/1 between points marked 2i/a and 2i/b on sheet 2 of the public rights of way plan
Temporarily closed along a route shown in yellow and diverted along a route contained within the diversion area shown hatched olive green on sheet 2 of the public rights of way plan to facilitate the construction of the authorised development
District of West Lindsey
Approximately 555 metres of Bridleway reference 9i Fill/86/1 between points marked 9i/a and 9i/b on sheet 9 of the public rights of way plan
Temporarily closed along a route shown in green and diverted along a route contained within the diversion area shown hatched olive green on sheet 9 of the public rights of way plan to facilitate the construction of the authorised development
District of West Lindsey
Approximately 473 metres of Footpath reference 11i Stow/83/1 between points marked 11i/a and 11i/b on sheet 11 of the public rights of way plan
Temporarily closed along a route shown in yellow and diverted along a route contained within the diversion area shown hatched olive green on sheet 11 of the public rights of way plan to facilitate the construction of the authorised development
District of West Lindsey
Approximately 345 metres of Bridleway reference 15i TLFe/31/2 between points marked 15i/a and 15i/b on sheet 13 of the public rights of way plan
Temporarily closed along a route shown in green and diverted along a route contained within the diversion area shown hatched olive green on sheet 13 of the public rights of way plan to facilitate the construction of the authorised development
District of Bassetlaw
Approximately 2,293 metres of Byway Open to All Traffic reference 19iv NT“Rampton”BOAT13 between points marked 19iv/a and 19iv/b on sheets 19 and 20 of the public rights of way plan
Temporarily closed along the route shown in blue and diverted along a route contained within the diversion area shown hatched olive green on sheets 19 and 20 of the public rights of way plan to facilitate the construction of the development
District of Bassetlaw
Approximately 83 metres of Footpath reference 19v NT“Rampton”FP20 between points marked 19v/a and 19v/b on sheet 19 of the public rights of way plan
Temporarily closed along the route shown in yellow and diverted along a route contained within the diversion area shown hatched olive green on sheet 19 of the public rights of way plan to facilitate the construction of the development
District of Bassetlaw
Approximately 84 metres of Byway Open to All Traffic reference 19vi NT“Rampton”BOAT12 between points marked 19vi/a and 19vi/b on sheet 19 of the public rights of way plan
Temporarily closed along the route shown in blue and diverted along a route contained within the diversion area shown hatched olive green on sheet 20 of the public rights of way plan to facilitate the construction of the development

---
Source: https://www.legislation.gov.uk/uksi/2024/943/schedule/6/part/2 (the official version)
Page: https://openlegislation.uk/cottam-solar-project-order-2024/schedule-6/part-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.