Chapter Construction

Original text. Later amendments are not shown.

The main structure over the river is an asymmetric cable–stayed bridge with a main span of 194 metres and an anchor span of 100 metres (which has been sub–divided into two unequal spans of 40 metres and 60 metres). The line of the new crossing is skewed to the river at an angle of approximately 40 degrees and crosses immediately downstream of British Steel plc’s jetty. During construction (estimated as being 30 months), there will be a requirement for access to the tower and anchor piers and for a platform on which to support temporarily the anchor span. Construction of the main span over the main navigation channel will be by cantilevering from the tower. This overcomes the need for supports from below the deck within the river and leaves the navigation channel uninterrupted for its full width.