OpenLegislation

Chapter Span and Tower

Original text. Later amendments are not shown.

The bridge will provide a clear span over the main navigation channel with a minimum air–space at design flood–level (036.0 metres O.D.) of 18.0 metres. During construction, this will be reduced to 16.0 metres to permit use of travelling falsework etc. It should be noted that normal high water levels on the spring tides are approximately 036.5 metres O.D. The tower to the bridge will be an inverted Y structure approximately 115 metres high and 50 metres wide at the base. This will be located behind the training breakwater, on the sand bank. Heavy foundations will be required to support the tower, but these will be below the general level of the sand bank and will not effect normal flows within the river.