# The County Council of Clwyd (River Dee Estuary Bridge) Scheme 1992 Confirmation Instrument 1993, Chapter: River Diversion


The normal navigable waterway will require diverting around the legs of the tower (which are approximately 5.0 metres square and are angled to the normal flow direction within the river), and where the west bank of the river requires realigning around the intermediate anchor pier. The bridge’s anchor piers are located in the flood bank of the river. Again, foundations will be below the existing ground level.
During the construction (referred to above), it is envisaged that a temporary causeway will be required over the flood and sand banks for the platform which is to be provided to support temporarily the anchor span. This will reduce, temporarily, the width of the navigable waterway.

---
Source: https://www.legislation.gov.uk/uksi/1993/2400/schedule/2/part/2/chapter/5 (the official version)
Page: https://openlegislation.uk/county-council-of-clwyd-river-dee-estuary-bridge-scheme-1992-confirmation-instrument-1993/schedule-2/part-2/chapter-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.