OpenLegislation

Article 3 Citation, commencement and interpretation

Original text. Later amendments are not shown.

A claim for compensation made under article 2 shall be submitted within 90 days of–

(a)

the final settlement date defined in section 87(2), or such later date as settlement of the purchase is made in terms of section 87(3) or (4);

(b)

the date of withdrawal by the crofting community body of its confirmation of its intention to proceed with the purchase under section 85; or

(c)

the date on which the crofting community body’s application is treated as withdrawn under section 87(5),

whichever date is the earlier.