In the City of London–
Work No. 1/23A– A temporary diversion of the London Bridge Sewer, commencing by a junction with that sewer beneath a point 12 metres south-west of the junction of Moorgate with Finsbury Circus, and terminating by a junction with that sewer beneath a point 25 metres south-west of that road junction;
Work No. 1/23B– A reinstatement of the London Bridge Sewer, commencing by a junction with that sewer beneath a point 12 metres south-west of the junction of Moorgate with Finsbury Circus, and terminating by a junction with that sewer beneath a point 25 metres south-west of that road junction;
Work No. 1/24– A diversion of the sewer in Liverpool Street commencing by a junction with that sewer beneath a point 10 metres south-east of the junction of Liverpool Street with Blomfield Street and terminating beneath a point 40 metres west of the junction of Liverpool Street with Old Broad Street. Work No. 1/24 includes shafts for construction and maintenance;
Work No. 1/24A– A cable tunnel commencing beneath a point 41 metres south-west of the junction of Old Broad Street with Liverpool Street and terminating beneath a point 28 metres north-west of that road junction. Work No. 1/24A includes a shaft for construction;

---
Source: https://www.legislation.gov.uk/ukpga/2008/18/schedule/1/paragraph/wrapper15n1 (the official version)
Page: https://openlegislation.uk/crossrail-act-2008/schedule-1/paragraph-wrapper15n1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.