# Crossrail Act 2008, Paragraph 13

Extent: E+W+S+N.I.

(1) Any dispute arising between the nominated undertaker and the undertakers under this Part shall be determined by arbitration if—
(a) the parties agree, or
(b) the dispute relates to the amount of any sum payable under this Part,
but shall otherwise by determined by a person appointed by the appropriate Ministers.
(2) Any person appointed by the appropriate Ministers under sub-paragraph (1) shall, in determining any dispute arising under this Part, have regard to such matters as may be specified by the appropriate Ministers on making the appointment.
(3) In this paragraph “the appropriate Ministers” means the Secretary of State for Transport acting jointly with either the Secretary of State for Environment, Food and Rural Affairs or the Secretary of State for Energy Security and Net Zero.

---
Source: https://www.legislation.gov.uk/ukpga/2008/18/schedule/17/part/2/paragraph/13 (the official version)
Page: https://openlegislation.uk/crossrail-act-2008/schedule-17/part-2/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.