The engineer’s approval under paragraph 38 must not be unreasonably withheld and any question of whether it has been unreasonably withheld is to be settled by arbitration under article 47 (arbitration) and the engineer’s approval or disapproval of the plans must be notified within 56 days of their submission.

---