No phase of the authorised development is to commence, including any preparatory earthworks or site levelling but excluding archaeological soil movement and ecological mitigation works, until a Construction Environmental Management Plan (“CEMP”) for that phase of development, drafted in accordance with the principles set out in the environmental statement, has been submitted to and approved in writing by the relevant planning authority. The CEMP must include—
(a) details of the methods to control noise and vibration arising from construction activities. These measures must include—
(i) proposals for monitoring of construction noise;
(ii) proposals for monitoring vibration; and
(iii) proposals for the introduction of mitigation measures or alternative working practices where the measurements exceed acceptable limits;
(b) details of the methods to be used to control dust and other emissions from the site;
(c) details of all temporary fencing, temporary buildings, compound areas and parking areas including arrangements for their removal following completion of construction;
(d) details of areas to be used for the storage of plant and construction materials and waste;
(e) details of the facilities to be provided for the storage of fuel, oil and other chemicals, including measures to prevent pollution;
(f) details of temporary lighting arrangements;
(g) measures to ensure that construction vehicles do not deposit mud on the public highway;
(h) a scheme for the routing of construction heavy goods vehicles accessing the site;
(i) details of mitigation measures to protect biodiversity interests within the site during the construction phases; and
(j) advisory signage at public access points advising of possible hazards including the potential for sudden noise.
The CEMP may be subject to alteration by approval in writing of the relevant planning authority. All construction works must be carried out in accordance with the CEMP as approved from time to time in writing by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2014/1796/schedule/2/paragraph/13 (the official version)
Page: https://openlegislation.uk/daventry-international-rail-freight-interchange-alteration-order-2014/schedule-2/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.