# The Daventry International Rail Freight Interchange Alteration Order 2014, Paragraph 19: Flood Risk and Surface Water Drainage

Extent: E+W+S

No part of the authorised development which encroaches upon the existing floodplain of the Clifton Brook Tributary, except the flood management works required to facilitate or mitigate the weir removal project (item (d) of Works No. 5), is to be brought into use until the completion of the weir removal project.

---