# The Daventry International Rail Freight Interchange Alteration Order 2014, Paragraph 5: Design and phasing of access and highways works

Extent: E+W+S

The access works and the highway works must be carried out in accordance with details submitted to and approved by the relevant body under requirement 4 and the undertaker must use reasonable endeavours to complete such works by no later than the triggers set out in the table below or such alternative later triggers as are agreed by the relevant bodies.
Access Works
(1)
(2)
(3)
(4)
tem
Works
Trigger
Relevant Body
1
Southern Access (General Arrangement Plan Document 2.14A) (Works No. 5(a)).
Prior to any occupation.
Daventry District Council.
2.
Northern Access (General Arrangement Plan Document 2.14B) (Works No. 5(b)).
Prior to the phase one rail works coming into use.
Highways Agency.
Highway Works
(1)
(2)
(3)
(4)
Item
Highway Works
Trigger
Relevant Body
3.
A5/A426 Gibbet Roundabout (Highway Works Framework Plan Document 2.13A) (Works No. 10(a)).
Prior to the occupation of more than 305,000 square metres of gross internal floorspace of the authorised buildings.
Highways Agency and Warwickshire County Council.
4.
M1 Junction 18 (Highway Works Framework Plan Document 2.13B) (Works No. 10(b)).
Prior to the occupation of more than 305,000 square metres of gross internal floorspace of the authorised buildings.
Highways Agency.
5.
A5 Lilbourne Crossroads (Highway Works Framework Plan Document 2.13D) (Works No. 10(c)).
Prior to any occupation.
Highway Agency.
6.
A5 Catthorpe Crossroads (Highway Works Framework Plan Document 2.13E) (Works No. 10(d)).
Prior to any occupation.
Highways Agency.
7.
A5/A428 Roundabout (Parklands) (General Arrangement Plan Document 2.13F) (Works No. 10 (e)).
Prior to any occupation
Highways Agency and Northamptonshire County Council.
8.
Pedestrian and Cycle Link to Crick (illustratively shown on Document 2.13I) (Works No. 10(f)).
Prior to any occupation.
Highways Agency and Northamptonshire County Council.
9.
Improvements to the pedestrian and cycle link to Hillmorton (illustratively shown on Document 2.13J) (Works No. 10(i)) or such alternative pedestrian and cycle link as may be agreed in writing by the Transport Review Group to reflect the development of the RRS urban extension.
Prior to the provision of Northern Access (item 2 above).
Warwickshire County Council.

---
Source: https://www.legislation.gov.uk/uksi/2014/1796/schedule/2/paragraph/5 (the official version)
Page: https://openlegislation.uk/daventry-international-rail-freight-interchange-alteration-order-2014/schedule-2/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.